Thursday, 21 November 2024
Carpets and concrete
Thursday, 14 November 2024
Keys!!
We finally managed to get our PCI inspection done on Wednesday the 30th of October. At the time of the inspection, our air conditioning hadn't been finished, nor did we have any glass balustrading on. This unfortunately meant that we weren't going to achieve key handover by November 1st as planned.
However, Stannard appreciated that we were in a tough position with our own finishing trades and kindly allowed us to access the house via our own builder's key so our trades could start. So on Monday 4th of November, the Art of Timber, our engineered wood floor contractor started work on site. We are getting wood up our stairs, across the first floor landing and into our master bed and robe.
After a week of work, the timber floors were nearly finished. It was then the turn of the balustrading people to install our glass balustrading, which went in on Monday 11th as planned. Three days later on November 14th, we went into Stannard's offices and officially completed handover and got the keys to our new house!
Wednesday, 23 October 2024
PCI delayed
Finishing work continues - we've seen the painters a lot doing cornicing, skirtings, door frames, doors and other fiddly bits, leaving the walls til last. Plumbers have been in doing various bits and pieces around the house, guttering downpipes have been installed, electricians have energised the house, things like towel rails, robe hooks, toilet roll holders, etc have been installed. We also now have a garage door. Perhaps the thing we were most excited about though was our void pendant. It looks awesome!
Last weekend the cleaners showed up and spent the entire weekend thoroughly cleaning the house. There was a team of them for literally 10 hours a day on both Saturday and Sunday cleaning. I hope that's not reflective of the cleaning effort we're going to have to do! Of course it won't be as they had to clean off two years plus of construction grime.
At this stage, we're two work days away from PCI and still need the following done: Air Con vents and outside compressor installed. frameless glass balustrading to be installed, mirror splashback to our bar area to be installed and painting to be finished. It's a pretty small list and with the exception of painting, can all probably be knocked off in a day's work or less for each required trade. They drilled the holes for the balustrading yesterday so with a bit of luck, that'll be installed today/tomorrow.We've been busy lining up trades for flooring, carpets, cupboards, aggregate, etc and have them all lined up to kick off on Nov 4th, with our intention to move in early December and be settled in time for Christmas. Just hope everything else (bed, mattress, furniture) will be ready for delivery on a similar timeframe.
Getting very exciting!
Wednesday, 25 September 2024
Heading toward PCI
Wednesday, 14 August 2024
Stone!
Exciting progress
Thursday, 18 July 2024
Unexciting progress
Again, I find myself a month after my last blog update with not a whole lot to really write about. Don't get me wrong, we've had pockets of progress but not exactly the stuff that makes good reading (not that I'm convinced any of my previous content does).
The tilers worked away for about 10 days on the upstairs bathrooms and balcony tiling and finished working up their around the 28th of June. From their, they tidied up, moved their stuff downstairs and then set about cleaning up the ground floor slab ready for pouring of a screed to all areas where the ground floor main tiling is occuring, as well as the laundry, guest ensuite and powder.On 1st of July they returned to pour the screed, taking two to three days to screen all the areas to be tiled. A necessary step toward completion but not exactly a shout from the rafters update. Perahps something a little more tangible in terms of progress came about 10 days later when they poured our garage floor grano and then another two days later again when they returned to pour the grano for the alfresco and my pool equipment room.
On Tuesday this week we saw the first load of our kitchen and laundry cabintry dropped off on site. Nothing was installed, they literally dropped it off and then left again. According to our fortnightly update, they should be back toward the end of the week to start installation. What the update didn't say is that the painters would be returning to apply the first two coats to the inside downstairs. On my usual cruise past the block on my way to work this morning, I found the painters on site cracking in. A pleasant surprise to be sure.So that's it, this update is literally about watching concrete and paint dry. Unexciting, but progress.
Tuesday, 18 June 2024
Tiling
Wednesday, 15 May 2024
Approaching lock up
It's been a month since my last blog update and as usual, there have been periods of lull and periods of really good activity.
The first week or so since my last update not a whole lot happened at the build, although we did see the first of our stone benchtops installed into the master ensuite, kids bathroom and kids powder, along with some basins. You may recall we changed our mind on our benchtops quite a long time after our initial selections and we're really happy we made the switch. The new benchtops are lovely. There was also some framing down to the ground floor roof where we are having bulkheads, soffits and coffered ceilings.We also made a post-build decision and have appointed Art of Timber as our preferred supplier for the suply and installation of our timber flooring that will go up the staircase, across the landing, down the upstairs hallways and insto the master bedroom and walk in robe. We've chosen a wide board blackbutt in a brushed matte finish. Can't wait to see it.
Early May saw the arrival of our bathroom tiles, which was a little earlier than expected but a pleasant surprise. The rendering team also arrived back to start the cement render inside and outside of the ground floor. They have been on site pretty much every working day for the last two weeks. They completed all the cement render and then started into the final plaster coat. In between the two coats, the glazier was out to install all the downstairs glass.Two days ago we saw the installation of two temporary doors, one at the front and one between the garage and the mudroom. These were actually locked for the first time yesterday in the first real sign of lock up. Yesterday we also had an on-site meeting with the tiler who talked us through his plan to lay out the tiles for our upstairs bathrooms. He will get started in earnest in the next few weeks. Finally, today, the ceiling fixer team in on site to install all the gyprock sheeting to our ground floor areas. A labourer team was also on site cutting a channel into our slab for the sliding door to the alfresco. It's a commercial stacking door and has an in-built sump drain so that it can sit flush with the flooring. We also need a plumber to come out and plumb this drain and also some more brickwork to be done before that door can be installed. Once it's in, we'll officially be a lock up!Thursday, 18 April 2024
Ground Floor Works
Friday, 22 March 2024
Ground Floor Roof Cover
Tuesday, 12 March 2024
More Ground Roof + Electrical
After a flurry of activity in the first two days of ground floor roof construction, the roof chippies disappeared for a couple of weeks. However, progress continued on a different front - the ground floor electrical. Speaking with the electricians, it seems the main roof chippie got injured at some point (unsure if on our site or not) and Stannard was organising another team to finish it off.
The electricians have spent many days on site over the last couple of weeks chasing cables through the spaghetti maze of pipework within the upper floor slab to provision wiring to all the ground floor light switches, power points, internet points, TV points and speaker points. They have then been fitting off the cables into the wall channels that were cut previously. A few channels were missed the first time so they were also marked out and a chasing company came in and did a few more cuts for the electricans to finish.
The electricans also ran the cabling through the new ground floor roof and into the single storey part of the house. There is now a mass of cabling leading into our garage, where both the electrical load centre and internet hub will be located. Pleasingly, another roof team also showed up to finish off the ground floor roof framing works so that the colourbond could be measured up and ordered. We've already had the guttering and downpipes delivered. Imagine we'll see the roof chippies return once the colourbond material arrives ready for roof cover to go on.Thursday, 22 February 2024
Ground Floor Roof
Monday, 5 February 2024
Upper storey revealed
Removal of the scaffold marks an exciting step as construction now moves to focus on the lower floor, starting with construction of the roof at the back half of the house, including the alfresco, which is also under the main roof. We are also looking forward to seeing the light come in from the skylight we optioned to have over the kitchen.
Once the roof is on, it's back to more render inside and out, installation of the door and window glass, including our large commercial sliding stacker door between the kitchen/dining and alfresco and our wide front door to get to lock up. Lock up is our next formal completion stage and the next time the builder gets cash so I'm hoping that incentive will see us power through the next phase. I've got a bet on with Josh that we reach lock up by March 31st. Two shiny dollars are at stake so fingers crossed!Wednesday, 24 January 2024
Ready for scaffold drop!
Happily, since the 17th, we've seen a few things happen. The first trade back to site was the tiling team, who came and screeded our master ensuite, the kids bathroom and the balcony. The next week, it was the rendering team, who first applied a paint sealer to all our external walls before coming back the next day to apply the acrylic render texture coat to the whole outside of the upper floor. At the same time, the tiling team came back and applied the waterproofing to the ensuite & kids bathroom. The painting team then reappeared to finish painting all the eaves of the house. The upstairs is really looking great!
Best as we can tell, there's nothing left that requires the scaffolding, perhaps just the drain down pipes, so hopefully we see the scaffolding dropped so work can start on the lower floor. At this point, the build looks like a house (upper floor) has been built on top of a construction site (ground floor).
We're excited to be moving to the ground floor part of the build. The upper floor is more of our "sleeping" zone of the house, while the ground floor is where we're going to do our living, so it will be great to see that start to come together.
Wednesday, 20 December 2023
More internal painting
So that's it for this year. It's been reasonably productive I guess. 2023 saw the upper floor formwork built, the upper floor concrete slab poured, the upper floor brickwork completed, upper floor roof frame, upper floor roof cover, upper floor rendered inside and out, upper floor walls plastered and painted, upper floor ceilings and cornices installed and painted, upper floor glass installed to windows and doors, external moulding installed to balcony and portico and all the plumbing, electical and air con work performed to the upper floor.
Hopefully this time next year we have keys and have started on the post-handover finishing items. See you all in 2024
Friday, 1 December 2023
Upper Floor: Glass, ceiling & plaster coat
This week was one of the busiest we've seen for our build yet.π
But before I get into that, we only had one thing happen last week - we had the our brickie team from the ground floor arrive back on site to finish bricking up the balcony. Previously they had left an access hole through the balcony to allow trades to get wheelbarrows through the balcony wall for all the cement render. That access was bricked up last week. Was a surprise to see our ground floor brick crew back but since to say g'day to the team again.
Onto the week that was. We had three different trades attend this week. Yep, you read that right, three! The glazier from Jason windows kicked things off Monday by putting in all our external windows and sliding door glass to our upper floor. He was all done by Monday afternoon. Tuesday saw an early delivery of gyprock and cornice materials followed shortly after by the attendance of the ceiling guys to start putting the ceilings in. They wasted no time and had pretty much finished putting it all up in one day. We love how the raised ceiling in our master bed is looking! They came back Wednesday morning to finish off what they hadn't got to as well as do the drywall sheeting to the void wall, which doesn't get the cement render treatment that most of the other walls receive.Friday the rendering team were back on site to finish rendering the external balcony now that the brickwork had been completed as well as start applying the smooth plaster coat to the internal walls. I was surprised at just how smooth this plaster coat goes on. No doubt that comes down to the skill of the trade and when you see the quality of the work we're getting, it does make all the waiting a bit more palatable.
Our fortnightly update that we got on Wed also suggested that the progress will continue in the coming weeks with ceiling guys back to put on the cornicing once the internal plaster work is done, a trade to come and apply our external mouldings (the materials were also delivered this week) and even the waterproofing to the upstairs wet areas are booked in to be done. Nice to get a good run of trades, especially this close to Christmas when I was expecting things to quieten down.
Tuesday, 31 October 2023
Scaffold Drop
We're now expecting to see renderers & plasterers on site to attend to both inside and out, air con ducting installed to the upper floor, ceiling and cornices installed and windows put in as the next steps. Basically they get the upper floor to "lock up". Fingers crossed we get a good run of these trades in November!
Monday, 2 October 2023
Roof Cover
It seems everything happened while we were away (as is always the case when you're watching something closely).
As part of the celebration of Cheryl, 11x Wylde's went south for a week down at Siesta Park, just outside of Busselton during the first week of school holidays for some well needed R&R. Back home at our build, things weren't quite so leisurely. Fortunately my neighbours are keeping us updated and half way through our trip down south, on Wed 27th September, I received a couple of messages to say that our roof cover was going on.
When we arrived back from Siesta Park on Friday the 29th, we found the house with the roof cover fully done, the upstairs plumbing all chased in and the electricians on site putting the final touches on chasing in the electrical wiring. Three trades in one week!Top Roof Cover is another project milestone, which of course means another bill, but also means another step closer. Our next major milestone is Lock Up, so there's going to be a fair bit happening to get to that stage. Naturally, I took the opportunity to fly the drone over the house to capture the roof cover in all its glory.
Also, randomly after flying the drone over, I noticed a few days later we now have a TV aerial. I don't know when that happened!
Friday, 8 September 2023
Roof framing
On Friday 1 September it was all action at our block with the arrival of our roof carpenter together with a crane. The crane spent a few hours lifting all the roof materials up into the upper floor and onto the scaffolding and the boys wasted no time cracking in. By the end of the day, we had the start of all the flat beams that the ceiling will attach to. We could also see where the raised ceiling recess will be for our master bedroom.
Unfortunately, winter wasn't quite done with Perth and we lost the next Monday and Tuesday to bad weather with no one on site. Wednesday the boys were back and by the end of the day, we had the start of our roof pitch. Another two solid days work on Thursday and Friday and by late Friday afternoon, the main roof structure was complete, flashing has been attached and they'd even started putting in the eaves material for the boxed eaves.Speaking with the tradies, they thought they had a day or two ahead of them still so hopefully the weather stays good and we see them first up next week.
Update 12/9: Cruising past the block late Monday it appears that the framing part of the roof construction has been completed. The wooden framing looks done to my untrained eye, the flashing is on and the eaves have been sheeted. Speaking with the Stannard team over the weekend, I understand they need the flashing on before they can measure up and order the colorbond roof cover so we won't see that for a couple of weeks I'd suggest. In the meantime, we are expecting to hear from the electrician to conduct our upper floor walkthrough to confirm all our electrical provisions. They'll then come and put that in. We should also see the plumbers on site to do all the pipework for the upper floor wet areas. At some point, the air con ducting also goes in but I'm not sure if that's before or after roof cover. Guess we'll see.Carpets and concrete
I had this really well thought out, perfectly spaced timeline of how we were going to get all our finishing trades through the house before ...