Tuesday 31 October 2023

Scaffold Drop

After a little over four weeks of waiting, today we finally saw the scaffold team back on site to drop the scaffold back down to the floor height of the upper floor. Stannard has really struggled with this scaffolding team and as a result have sought alternate vendors. Unfortunately we're stuck with the under performing mob and the long waits that come each time we need scaffolding moved. Fortunately it should stay where it is now until they are fully finished with our upper floor. 

We're now expecting to see renderers & plasterers on site to attend to both inside and out, air con ducting installed to the upper floor, ceiling and cornices installed and windows put in as the next steps. Basically they get the upper floor to "lock up". Fingers crossed we get a good run of these trades in November!