Wednesday 20 December 2023

More internal painting

 The last official work week for the year before Stannard went on festive break saw the painters return to continue painting the inside of the upper floor. They applied a second coat to all internal walls and fully painted the ceilings and cornicing. It's so white and bright walking around upstairs now 😀It actually is looking more like a home than a construction site up there. According to the painter, we should expect to see the external renderer after Christmas, but I suspect that means after the Christmas break, i.e. early to mid January.  

So that's it for this year. It's been reasonably productive I guess. 2023 saw the upper floor formwork built, the upper floor concrete slab poured, the upper floor brickwork completed, upper floor roof frame, upper floor roof cover, upper floor rendered inside and out, upper floor walls plastered and painted, upper floor ceilings and cornices installed and painted, upper floor glass installed to windows and doors, external moulding installed to balcony and portico and all the plumbing, electical and air con work performed to the upper floor.

Hopefully this time next year we have keys and have started on the post-handover finishing items. See you all in 2024

No comments:

Post a Comment

Heading toward PCI

Wow, it's been over a month since my last update but this time that's not due to a lack of activity at the build, I've just not ...