Ground Floor Roof Cover

Monday afternoon I was doing one of my usual drive-by's of our build site on my way home from work and was surprised to see a truck parked out the front making a delivery. Naturally I stopped for a chat and it turned out he was asked to do a late delivery of our ground floor roofing colorbond materials as the roofies would be starting the job the next day.

We were therefore a little disappointed when Tuesday brought about no progress at our site, nor any Wednesday (although there was a brief appearance by the sparkies), nor any progress Thursday. Happily though, Friday saw a team of roofies appear on site and they quickly went to work installing all the ground floor roof cover, including the little bit of roof over one side of the garage. It was a pretty long day for them as they were still finishing off by school pick up time, despite the typically early tradesperson start time.

Another step closer to lock up. Still no sign of the plumbers as yet but hopefully we'll see them, the skylight people and the air-con guys show up. Alternatively, they could come and install the glass to all the lower floor windows and doors, install the front door, alfresco slider and the door between the house and the garage and we'd be at lock up! I'd be happy with either and any progress is good progress.

No comments:

Post a Comment

Carpets and concrete

I had this really well thought out, perfectly spaced timeline of how we were going to get all our finishing trades through the house before ...