Scaffold

The upper floor slab had now had a decent time to cure and finally on June 1st the scaffold team showed up to erect the scaffold around our ground floor in preparation for commencement of brick work to our upper floor. 

It took the guys three pretty much full days to frame out the scaff around our house, including putting scaff in our void area. A week after the scaff guys arrived our brick lift showed up. Talking with the scaffold guys they suggested bricks were due Friday June 9 with brick layers following the week after. Here is a pic of the house awaiting bricks.

Recently while we've been waiting we did go back and have a look at our benchtop selection and we're now inclined to change our previous selection, which is used all through the house, to something different. We're just waiting on that variation to come through to make a decision on. Will update on our new selection later.

There does appear to be a bit of freeing up of resources we're seeing in builds around the place so fingers crossed we can move through some/all of the next stages with less waiting between each step. Would love to also not have so long between blog posts!

No comments:

Post a Comment

Heading toward PCI

Wow, it's been over a month since my last update but this time that's not due to a lack of activity at the build, I've just not ...