Thursday, 29 June 2023

Sign of Movement

After yet another wait for labour, we had our first sign of actual construction related movement on the block yesterday. We were meant to get a brickie team a few weeks back but apparently Stannard lost a team to another builder, which threw a spanner in to their scheduling works. Yesterday's update from Sam, our construction coordinator, however, was a little more positive, stating we should expect to see a brick layer on site this week for preparation with construction to commence next week.

True to her word, today Amanda drove past our block and found Adam, a bricklayer assigned to our upper floor, on site. Adam is a solo bricklayer, supported by his Dad, and built another Stannard home one suburb over, so we're familiar with his work. Also, Dean, our design consultant spoke highly of Adam prior to our build commencing, so we know he's a bit of a gun bricklayer and that we're going to get a quality product from him.

Adam got a lot of things prepared during the afternoon, marking out where all the external and internal walls needed to go and getting materials ready for a start in the coming days. He even put up a few things like placing some of our void windows. Hopefully the weather holds out, although there is rain forecast, as we're very much feeling overdue to see some actual construction on our house! Stay tuned.

Wednesday, 14 June 2023

Upper floor bricks


Just a quick update. Today saw the loading of our upper floor with bricks ready for the next phase of brickwork. We did have a brick delivery two days ago but it was only a small load and left stacked on verge. Today's load went straight onto top slab, along with moving the first load up there.

The upper floor will bring our three main bedrooms, our master ensuite and robe, the kids bathroom, our sitting room, a study nook and it balcony. Hopefully we get some good news about the brick layers soon.

15/6: We had some door frames delivered today :)

Thursday, 8 June 2023

Scaffold

The upper floor slab had now had a decent time to cure and finally on June 1st the scaffold team showed up to erect the scaffold around our ground floor in preparation for commencement of brick work to our upper floor. 

It took the guys three pretty much full days to frame out the scaff around our house, including putting scaff in our void area. A week after the scaff guys arrived our brick lift showed up. Talking with the scaffold guys they suggested bricks were due Friday June 9 with brick layers following the week after. Here is a pic of the house awaiting bricks.

Recently while we've been waiting we did go back and have a look at our benchtop selection and we're now inclined to change our previous selection, which is used all through the house, to something different. We're just waiting on that variation to come through to make a decision on. Will update on our new selection later.

There does appear to be a bit of freeing up of resources we're seeing in builds around the place so fingers crossed we can move through some/all of the next stages with less waiting between each step. Would love to also not have so long between blog posts!

Carpets and concrete

I had this really well thought out, perfectly spaced timeline of how we were going to get all our finishing trades through the house before ...