Thursday, 23 June 2022

Earthworks

Monday the 20th the surveyors were out re-pegging the block for boundaries, levels, etc. Two days later the earthworks started to level out the block ready for compaction and then ground floor slab. 

Super exciting to see some progress towards the build. It's quite amazing to see how level they get the ground and so quickly. Can even see the step down in the sand levels for where the garage will be. 

Our site supervisor, Joseph, also gave me a call today just to say g'day and let me know he had our file and that work was commencing. He was just waiting to hear back from his concrete guy to lock in a date to get the slab down but said compaction should occur over the next few days, then testing of the compaction. After that we'll be ready for slab, which, with a bit of luck, we should see go down inside of the next couple of weeks. Stay tuned!

No comments:

Post a Comment

Carpets and concrete

I had this really well thought out, perfectly spaced timeline of how we were going to get all our finishing trades through the house before ...