Resort on Rankin - Build Blog
Thursday, 21 November 2024
Carpets and concrete
Thursday, 14 November 2024
Keys!!
We finally managed to get our PCI inspection done on Wednesday the 30th of October. At the time of the inspection, our air conditioning hadn't been finished, nor did we have any glass balustrading on. This unfortunately meant that we weren't going to achieve key handover by November 1st as planned.
However, Stannard appreciated that we were in a tough position with our own finishing trades and kindly allowed us to access the house via our own builder's key so our trades could start. So on Monday 4th of November, the Art of Timber, our engineered wood floor contractor started work on site. We are getting wood up our stairs, across the first floor landing and into our master bed and robe.
After a week of work, the timber floors were nearly finished. It was then the turn of the balustrading people to install our glass balustrading, which went in on Monday 11th as planned. Three days later on November 14th, we went into Stannard's offices and officially completed handover and got the keys to our new house!
Wednesday, 23 October 2024
PCI delayed
Finishing work continues - we've seen the painters a lot doing cornicing, skirtings, door frames, doors and other fiddly bits, leaving the walls til last. Plumbers have been in doing various bits and pieces around the house, guttering downpipes have been installed, electricians have energised the house, things like towel rails, robe hooks, toilet roll holders, etc have been installed. We also now have a garage door. Perhaps the thing we were most excited about though was our void pendant. It looks awesome!
Last weekend the cleaners showed up and spent the entire weekend thoroughly cleaning the house. There was a team of them for literally 10 hours a day on both Saturday and Sunday cleaning. I hope that's not reflective of the cleaning effort we're going to have to do! Of course it won't be as they had to clean off two years plus of construction grime.
At this stage, we're two work days away from PCI and still need the following done: Air Con vents and outside compressor installed. frameless glass balustrading to be installed, mirror splashback to our bar area to be installed and painting to be finished. It's a pretty small list and with the exception of painting, can all probably be knocked off in a day's work or less for each required trade. They drilled the holes for the balustrading yesterday so with a bit of luck, that'll be installed today/tomorrow.We've been busy lining up trades for flooring, carpets, cupboards, aggregate, etc and have them all lined up to kick off on Nov 4th, with our intention to move in early December and be settled in time for Christmas. Just hope everything else (bed, mattress, furniture) will be ready for delivery on a similar timeframe.
Getting very exciting!
Wednesday, 25 September 2024
Heading toward PCI
Wednesday, 14 August 2024
Stone!
Exciting progress
Thursday, 18 July 2024
Unexciting progress
Again, I find myself a month after my last blog update with not a whole lot to really write about. Don't get me wrong, we've had pockets of progress but not exactly the stuff that makes good reading (not that I'm convinced any of my previous content does).
The tilers worked away for about 10 days on the upstairs bathrooms and balcony tiling and finished working up their around the 28th of June. From their, they tidied up, moved their stuff downstairs and then set about cleaning up the ground floor slab ready for pouring of a screed to all areas where the ground floor main tiling is occuring, as well as the laundry, guest ensuite and powder.On 1st of July they returned to pour the screed, taking two to three days to screen all the areas to be tiled. A necessary step toward completion but not exactly a shout from the rafters update. Perahps something a little more tangible in terms of progress came about 10 days later when they poured our garage floor grano and then another two days later again when they returned to pour the grano for the alfresco and my pool equipment room.
On Tuesday this week we saw the first load of our kitchen and laundry cabintry dropped off on site. Nothing was installed, they literally dropped it off and then left again. According to our fortnightly update, they should be back toward the end of the week to start installation. What the update didn't say is that the painters would be returning to apply the first two coats to the inside downstairs. On my usual cruise past the block on my way to work this morning, I found the painters on site cracking in. A pleasant surprise to be sure.So that's it, this update is literally about watching concrete and paint dry. Unexciting, but progress.
Carpets and concrete
I had this really well thought out, perfectly spaced timeline of how we were going to get all our finishing trades through the house before ...